The pond at Roswell Area Park is full again. Crews spent close to a year dredging it, rebuilding the embankment, adding forebays and redoing the trail around the water. Native and aquatic plants now line the edge, and logs were placed as habitat for turtles. The City says turtles and frogs started coming back on their own before construction even wrapped up. The ribbon cutting was Thursday, Sept. 10, and Roswell Connections puts the job at about $3.1 million.
Four miles of riverbank tell a different story. Riverside Park, at 575 Riverside Road, has been behind construction fencing since spring. Its sprayground is closed and the Riverside Sounds concert series is on hold. This fall, Roswell's finished park projects are all inland. The Chattahoochee corridor is the part still being built.
The Money Followed the Ballot's Biggest Line
Roswell voters approved Question 1 in 2022. It authorized up to $107.6 million for recreation, parks, bike and pedestrian paths, and sidewalks. Comparing a few of the line items shows where the city should look different first.
| Bond line item | Approximate allocation | Where it stands, fall 2026 |
|---|---|---|
| Roswell Area Park | $20 million | Pond, three multi-use fields, and community building complete; smaller work wrapping up |
| Four river parks combined: Riverside, Roswell River Landing, Azalea, Don White Memorial | About $24.7 million | Riverside under construction; Don White in design |
| Hembree Park | $10.2 million | Gym renovation underway; larger park plan in design |
| East Roswell Park | $8.6 million | Dog park, trail loop and turf fields complete; remaining playground equipment still being installed |
One inland park got nearly as much as all four river parks put together. Roswell Area Park's work could also be broken into smaller pieces and finished in stages. The river money is mostly tied up in a single large rebuild. The City's bond dashboard puts the Riverside construction estimate at $14,778,451.
Roswell Area Park Is the Finished Version
If you want to see what the bond was meant to produce, go to Roswell Area Park. The bond dashboard lists multi-use fields 1, 2 and 3 and the Bill Johnson Community Activity Building as complete. Repaving of the park's roads and parking lots was marked 100% complete in September. The pond project added 35 trees across the work area.
The pond has one limit. Fishing is still off-limits while the City stocks about 15,000 fish in phases as the water settles. The City expects fishing to reopen in late summer or fall 2027. For this season, the pond is for walking, not for casting a line.
A few smaller jobs at the park are still underway, according to the City's 2026 Capital Project List, revised October 2026:
- Sidewalk replacement around two playgrounds and under Pavilion #1, 90% complete, with a November 2026 target
- Bleacher replacement, swapping wooden bleachers for ADA-compliant aluminum, 50% complete and already started at Field 3, with a December 2026 target
- Pool house and concession renovation, in planning, with a May 2027 target
- Pool renovation, 30% through design, with a May 2028 target
Other inland parks show the same pattern. On Sept. 24, Grimes Bridge Park reopened Soccer Fields 1 and 2 with artificial turf where there used to be grass. The project also rebuilt a retaining wall and restored a detention pond, and 29 more trees were planned for this fall. At East Roswell Park, the dog park has grown from half an acre to three-quarters of an acre, and a new trail loop circles the park. The last of the playground equipment is still being installed. Inside the Hembree Park gym, the new court floor was scheduled for completion on Oct. 2, with a week of curing before the rest of the work resumes. The renovation, which also includes new goals, bleachers and LED lights, is aimed at December.
Night games also look different. On Oct. 2, the City reported that it had replaced 699 metal-halide fixtures on 167 poles at athletic fields and racquet courts with LEDs. It estimates the switch cuts energy use by 54%.
On the River, the Gap Lasts Until Summer 2027
Riverside Park's groundbreaking was Friday, March 13, 2026. In October, the City's capital list put the project at 40% complete. Crews are working on the bandstand and the footers for the event pavilion, and steel is going up for the buildings. The target completion is June 2027. The City's Riverside Park page still says to expect a Summer 2027 reopening. Treat any date that far away as a target that could move.
The finished park will include ADA-accessible restrooms, an open-air pavilion, a better bandstand, a nature-themed playground and an updated sprayground that stays free to use. The tree count is the change people will see first. The project removed 221 trees, 14 of them specimen trees, and plans to plant 307 native and canopy trees. So the park will reopen with more trees than it had before, but most of them will be young plantings rather than mature shade.
You can still get to the river while the park is closed. The City says pedestrian routes along the site will stay open for the whole project and that traffic on Riverside Road won't be affected. Alternate parking is at Ace Sand Park, 705 Riverside Road, and Don White Memorial Park, 925(B) Riverside Road. Azalea Park and River Landing are excluded as alternate parking.
Both of those parking lots have their own projects coming. Ace Sand Park's Phase II, which includes a children's stormwater garden, a parking lot and landscaping, was 95% through design on the October list. Don White Park was 60% through design, with no completion date. Its timing is tied to the separate Riverside Road project. That means the river corridor is likely to have active work well after Riverside itself reopens.
The Trails That Work Right Now
Two trail options let you skip the construction entirely. At Vickery Creek and Old Mill Park, the designated trails are open. The City's Vickery Creek page says getting into the creek or the waterfall is prohibited, and it sends visitors to its official viewing areas instead. On the Big Creek Greenway, the boardwalk work is long finished. The City replaced 1,950 feet of boardwalk and reported it complete in September 2024.
Into December, the Calendar Stays Inland Too
The City-listed events for the rest of the year follow the same map. None of them are at the river parks:
- Invasive Plant Workshop, Saturday, Nov. 7, at East Roswell Park, hosted by Keep Roswell Beautiful and the City
- Roswell Holiday Expo, Nov. 27 from 4 to 7 p.m. and Nov. 28 from 11 a.m. to 4 p.m., at the Mimms Museum of Technology and Art. It's free, with vendors, Santa and a kids' zone.
- Lighting of the Christmas Tree, Dec. 4 from 6 to 8 p.m., at Heart of Roswell Park, with choral performances, hot chocolate, fire pits with s'mores, Santa and a 40-foot tree
- Roswell Makers Market, Dec. 5 from 10 a.m. to 5 p.m., at the Roswell Visual Arts Center, presented by Roswell Creative Arts and the City. This free indoor market has youth and adult makers and a Winter Wonderland photo setup.
Riverside Sounds is the river's usual contribution to the calendar, and the City lists it as on hold until further notice. Until the park reopens, the season's outdoor gatherings will happen at the inland parks and downtown civic spaces the bond has already finished or never needed to touch.
Park investment like this affects how a Roswell home is valued, whether it sits within walking distance of the renovated Roswell Area Park or close to a Riverside that won't reopen until next summer. If you'd like to talk about how projects near your street fit into your home's value, Stevens Residential can walk you through it. Schedule a Free Market Consultation.